My experience with BKV was really good. BKV fulfilled all three important points: Safety, Quality and project dateline. What I like about BKV is cooperation. Never the less how challenging the project is, the BKV team never complains or says it’s impossible. They come with new ideas and look for the best solutions.
Windfarm Lummen Puratos
ContractorNordex
CraneTC2800
ProjectConstructing 1 wind turbine
TypeN117 TS120
Hub height120m
LocationBelgium, Lummen
We built a new wind turbine in Lummen Puratos with the TC2800. When building the crane we did not have much space to our capacity, that was a tough but good challenge. The construction of the wind turbine went very smoothly!