Windfarm Villers

More details

Clear agreements.

Ben van Zuijl

Projectmanager Vestas

As a project manager, I was able to make good agreements with BKV at management level, even with the transport delays we had on this project. We have sought solutions together with good consultation to minimize costs and delays. On site, the Vestas and BKV teams worked together in a safe and harmonious manner. The project has been completed successfully.

BKV as trusted wind partner in Europe provided off-loading and main installation cranes for Vestas V117 4.2 MW HH 91.5m wind turbine at windfarm Villers 7. For off-loading all components, the team planned to use LTM1250-5.1 (250t) and LTR1100 (100t). For main installation we used the LG1750 (750t) and the LTR1100 (100t). They were relocated from the north part of Netherlands, about 300 km from the project site and delivered by 41 trucks and assembled in 5 days. The project was executed in good and safe way.